The Rail Yard Progress
Slated for completion in July of 2021, The Rail Yard is currently one month ahead of schedule in our building timeline! Check back regularly for updates on the construction of these brand new townhomes and apartments!
Last Week
of February
A little snow doesn’t slow us down!
First Week
of February

Windows are starting to go in and we’ll be weather tight to begin interior finishes.
Last Week
of January

Ahead of Schedule
All Townhouses to be 100%
Complete by End of Semester!
We’re working faster than how fast January flew by.
Third Week
of January
Working right down the line.
First Week
of January
Paving is underway!

Fourth Week
of December
Building 400 is under roof.

First Week
of December

Second story underway!
Thanksgiving
Weekend

Sticks are in the air!
Third Week
of November

First slab is poured. Framing to start 11/17. Still on pace to be done by Cinco de Mayo.
Spring 2020
Demolition begins!
Down goes Dickinson Hall.
Last Week
of October
Ahead of Schedule
Townhouse Building 200
Projected for completion June 8th
Townhouse building 200 concrete is proceeding ahead of schedule.
Going vertical soon!
First Week
of November
Concrete is in the ground for the last set of townhomes. Right on schedule to be completed before Memorial Day.

First Week
of November

Plumbing is in the ground for townhouse building 400.
Second Week
of November

Ahead of Schedule
Townhouse Building 400
Projected for completion May 5th
Townhouse building 400 passed underground plumbing inspection; slab going in next week.