
The Rail Yard Progress
Slated for completion in July of 2021, The Rail Yard is currently one month ahead of schedule in our building timeline! Check back regularly for updates on the construction of these brand new townhomes and apartments!
Second Week
of June
A rainy day can’t stop us! We’re 100% under roof on every building! On pace for a strong finish.

First Week
of May
Townhouse Building 400
Cinco de Mayo
Completion date met!




Third Week
of March
Drywall has begun! Trim, doors, and paint up next! Still on pace for Cinco de Mayo COMPLETION!
Second Week
of March
Fully insulated walls and ceilings to lessen sound transfer and utility bills!
Last Week
of February
A little snow doesn’t slow us down!
Second Week
of February
Starting to see a glimpse of the final design.

First Week
of February
Windows are starting to go in and we’ll be weather tight to begin interior finishes.
Last Week
of January
We’re working faster than how fast January flew by.
Third Week
of January
Working right down the line.
First Week
of January
Paving is underway!
Fourth Week
of December
Building 400 is under roof.
Third Week
of December
Almost ready for the roof of building 400.

First Week
of December
Second story underway!
Thanksgiving
Weekend
Sticks are in the air!
Third Week
of November
First slab is poured. Framing to start 11/17. Still on pace to be done by Cinco de Mayo.
Spring 2020
Demolition begins!
Down goes Dickinson Hall.




First Week
of October
Storm water management system nearly complete.

Last Week
of October
Ahead of Schedule
Townhouse Building 200
Projected for completion June 8th
Townhouse building 200 concrete is proceeding ahead of schedule.
Going vertical soon!




First Week
of November
Concrete is in the ground for the last set of townhomes. Right on schedule to be completed before Memorial Day.
First Week
of November
Plumbing is in the ground for townhouse building 400.
Second Week
of November
Ahead of Schedule
Townhouse Building 400
Projected for completion May 5th
Townhouse building 400 passed underground plumbing inspection; slab going in next week.

Third Week
of April
Paint & Trim Installed ✅
Flooring Installed ✅
Kitchen Cabinets Installed ✅
It’s almost complete!
Fourth Week
of March
Brick layers on site. Final facade a few days away!
Last Week
of June
Every building is completely weather tight! Making the interior finishes the priority.
Last Week
of July
Closer to completion!
Check out the completed apartment building exterior. Picture youself relaxing on that awesome balcony! A sea of blue loveseats. Furniture Installation is happening now!




